The Member of Parliament for Salaga South, Hajia Zuwera Mohammed Ibrahimah, on Wednesday, May 6, 2026, inspected ongoing rehabilitation works on the Salaga–Sabonjida stretch of the main Bimbilla–Salaga road to assess the progress of the project.
During the inspection, the MP observed that the Sabonjida–Kunkaw section has been successfully tarred, while construction works are actively ongoing on the Kunkaw–Nkwanta stretch, where grading and gravel overlay activities are currently underway.
Hon. Zuwera Mohammed Ibrahimah expressed satisfaction with the pace and quality of work being carried out by the contractors.
She also commended the efforts being made to improve the road network, noting that the project will significantly enhance transportation, boost economic activities, and improve connectivity within the area